Up to 5,000 feet
Table says “See note.” The note directs Risk Category I and II buildings below 5,000 feet to the ASCE hazard tool. Confirm the boundary case with the county.
Sacramento / Placer / El Dorado
A carport in the Sacramento valley and a garage higher in the foothills may need very different designs. Use the parcel, elevation and current code—not a generic “snow-rated” label—to start the conversation.
By Bryan Lee · Mechanical engineering background
Sources checked November 16, 2026
Ask for the site-specific ground snow load and the resulting roof design loads, with the code edition and units written down. Ground snow load describes snow on the ground; roof design also accounts for the building and its surroundings. They are not interchangeable numbers.
California’s 2025 building standards took effect January 1, 2026. The project’s reviewing authority determines the applicable code and local amendments. California Building Standards Commission: current codes.
For 2026 projects, Placer’s current snow-load provisions direct designers to the applicable code method and ASCE hazard data. Its older A-16-C and A-16-D elevation tables should not be used as a universal current buying guide. Confirm the parcel’s elevation and the required load with Building Services.
Placer County designer resources and code links · Current code sections 15.04.290 and 15.04.360.
The county publishes a Parcel Data and Building Design Criteria lookup. Have the Assessor’s Parcel Number ready. The lookup itself cautions that its information may not be accurate; confirm the result with Building Division for the proposed structure and current code.
Use the criteria for your parcel and proposed building. A neighboring county’s elevation table does not establish the requirement for your property. El Dorado County current codes.
Examples from the ASCE Hazard Tool on November 16, 2026; your parcel decides.
These are five representative map points, using ASCE/SEI 7-22, Risk Category II and customary units. They are ground loads (pg), not roof design loads or town-wide requirements.
| Location | Point elevation (ft) | Ground snow (lb/ft²) |
|---|---|---|
| Roseville | 163 | 8 |
| Auburn | 1,256 | 23 |
| Cool | 1,523 | 26 |
| Placerville | 1,865 | 34 |
| Pollock Pines | 3,977 | 138 |
Coordinates are latitude, longitude. Point elevations use NAVD 88; mapped elevations come from the snow dataset.
The tool’s snow grid can differ from the point elevation, especially on steep terrain. At the Pollock Pines example, the point is 3,977 ft and the snow map is 3,778.9 ft. Have the designer and reviewing authority resolve elevation differences and confirm the parcel’s applicable criteria.
Source: ASCE Hazard Tool, ASCE/SEI 7-22, Figures 7.6-1 and 7.6-2 A–D. Check your exact parcel, code edition, risk category and local amendments before using a number for an order or design.
The following is a limited example from Placer County section 15.04.290, Table 1609.3(2), for Risk Category II. It is not a statewide rating or a determination of your building’s risk category.
Table says “See note.” The note directs Risk Category I and II buildings below 5,000 feet to the ASCE hazard tool. Confirm the boundary case with the county.
130 mph
140 mph
150 mph
The county describes these values as 3-second gust speeds at 33 feet above ground for Exposure C. Exposure, terrain, enclosure and building use also matter. A speed on a brochure alone does not establish that a building fits your site.
Source: Placer County designer resources → current county code, §15.04.290. Check the applicable California code and local amendments with the city or county reviewing your parcel.
The design may require different members, connections, bracing or frame spacing. Fewer feet between posts can affect vehicle doors and access. Have the quoted layout and openings checked against the engineering rather than changing the spacing on site.
Ask whether a gauge refers to the frame or roof panels. Material thickness alone does not establish snow or wind capacity: section shape, steel properties, spans and connections are part of the system.
The loads must reach suitable ground through the connections, anchors and foundation. A roof rating does not prove that an existing slab or soil-anchor arrangement is adequate. Compare gravel, concrete and dirt bases.
Ask for the actual design documentation, applicable loads, site assumptions and installation details. A generic certificate is not the same as the drawings accepted for your site.
El Dorado County’s residential accessory-structure checklist calls for foundation and framing information and relevant design documents. Confirm the current submission requirements before ordering.
Keep these answers with the quote. The building supplier’s site-specific engineered drawings and the reviewing authority’s requirements decide the configuration; this guide does not calculate a design.
Start with the location, intended use and approximate size. We connect you with a suitable local metal building company for a written quote. Ask that company to confirm the design criteria, installation and foundation responsibilities before you order.
Gold Country Metal Buildings is a quote-request service, not the manufacturer, installer or engineering provider.